Thruway Mainline Reconstruction and Widening
Pavement Reconstruction Needs
The condition and maintenance history of the pavement on the Thruway within
the Albany Corridor shows that the pavement is in need of replacement.
The original Portland Cement Concrete (PCC) pavement was originally designed
to last 50 years and has reached the end of its design life. The condition
of the PCC pavement is affecting the riding surface, requiring frequent
maintenance treatments. These treatments typically consist of milling off
the surface and replacing with an asphalt concrete overlay. Although these
treatments improve the riding surface for a period of time, pavement condition
reports have shown that the life of the surface treatments is decreasing.
This means that the surface treatments need to occur more frequently, resulting
in exorbitant costs. The only way to properly address the pavement condition
is through major reconstruction.
Based on the pavement surface condition and the frequency of maintenance
activities, reconstruction of the pavement is estimated to be needed in
or before the following years:
Interchange 21A to Interchange 22 - 2010
Interchange 22 to Interchange 23 - 2010
Interchange 23 to Interchange 24 - 2004
Interchange 24 to Interchange 25 - 2006
Interchange 25 to Interchange 25A - 2009
Capacity Needs
The growth in traffic volumes on the Thruway between Interchanges 22 to
25 has resulted in congestion during peak periods of travel. The traffic
analyses show that traffic volumes on three sections within the Albany
Corridor will approach or exceed the capacity of the highway in the near
future. These conditions will cause traffic congestion, which needs to
be addressed. The traffic analyses show that capacity improvements will
be needed by the year indicated below for these three sections:
Interchange 22 to Interchange 23 - 2010
Interchange 23 to Interchange 24 - 2005
Interchange 24 to Interchange 25 - 2003
Traffic analyses show that the addition of a travel lane in each direction
on these sections will provide the capacity needed to meet traffic volumes.
The remaining sections, Interchange 21A to 22 and Interchange 25 to 25A,
are expected to continue to provide adequate capacity for the traffic volumes
through the year 2024.
Interchange 23 to 24 Reconstruction and Widening
The section between Interchange 23 and 24 shows the most urgent need for
reconstruction. Consequently, the Thruway Authority anticipates began
preliminary design in 2004 of a project to address the reconstruction
needs. During construction of the project, a third lane will need to be
added in each direction, at least temporarily, to maintain two lanes of
traffic in each direction. Since the traffic analysis shows that an additional
lane is needed by 2005, constructing the third lane as a permanent lane
would meet the capacity needs and be more economical than constructing
a temporary lane. Therefore, the project will proceed as a reconstruction
and widening project on the Thruway between Interchanges 23 and 24. The
Thruway Authority anticipates that the third lane in each direction can
be added in the median without moving lanes closer to properties along
the Thruway’s right-of-way.
|