Frequently Asked Questions
Q - Why
are the Thruway Authority and the Department of Transportation undertaking
this project?
A - The project is being undertaken to improve
the connections between I-84 and I-87 (Thruway). The existing I-84/I-87 interchange
requires interstate traffic to utilize a local arterial (Route 300) to connect
to the two interstates. Rapid growth in the Newburgh area has increased local
traffic volumes on Route 300. This increase of local traffic, combined with
an increase in volumes connecting between the two interstates, has resulted
in traffic and safety concerns, primarily at the junctions with Route 300.
Traffic analyses indicate that eliminating the interstate traffic component
will greatly improve the safety of operations along the Route 300 corridor
and reduce the volume of large trucks by 30 percent. The proposed improvement
will simultaneously simplify interstate-to-interstate connections.
Q - How
much will the project cost?
A - The combined cost of the three construction
contracts is estimated at $120 million.
Q - How
will the project be funded?
A - The project will be funded by a combination
of Federal, NYS Thruway Authority and NYSDOT Funds.
Q - When
did construction begin? When will construction end?
A - Phase 1 of construction
began in August 2003. Phase 2 began in the Spring of 2006, and Phase 3 began in the Spring of 2007, with a completion date of August 2009.
Q - Will
crews be working at night?
A - Night activities are expected to
be limited to the installation of utilities across busy roadways and the
erection of steel for the three bridges that will cross over I-84. At
each bridge crossing, intermittent traffic stoppages are expected to last
approximately one week.
Q - What
type of construction will be done during the day? How will this
affect traffic?
A - The daytime work will involve the re-grading
of the interchange, construction of the new ramps and bridges, and the relocation
of the maintenance and toll facilities affected by the project. Work will also
be undertaken on Route 300 to facilitate the new interchange configuration
and maintain local access to both interstates. Traffic will be largely unaffected
by construction as the work will be staged to minimize impacts to the traveling
public. No off-site detours will be required as all movements within the interchange
will be maintained for the duration of construction.
Q - Will
property be taken? If so, how will owners be compensated?
A - The proposed project will not take property
from any residential landowner. The project will acquire property from
three commercially zoned parcels. Two of the three are presently undeveloped.
The one developed parcel is the Newburgh Mall property, from which 0.4 acres
of parking area and associated drainage channels will be taken. Monetary
compensation will be provided to the owners of the properties at fair market
value at the time of purchase.
Q - Will
toll collection be eliminated at the Newburgh Interchange?
A - Elimination of toll collection at
the Newburgh Plaza was considered during the evaluation of design alternatives.
Studies determined that in order to maintain current toll revenues (a
requirement of the Authority's bond holder covenants) a new mainline
plaza would need to be constructed north of Interchange 17. The estimated
direct cost (construction of a 16-lane toll plaza in both directions)
and indirect costs (right-of-way acquisition, environmental impacts, disruption
of mainline Thruway traffic) indicated that it would be more cost effective
and cause less impacts to maintain toll collection at Interchange 17.
Q - Is
this project related to the Stewart Airport Access (Drury Lane)
project?
A - The proposed project is independent of
the Drury Lane project. The project improvements accomplish different goals.
The goals of this project include improving safety and operations on Route
300, as well as improved interstate-to-interstate connections between I-84 & I-87.
Q - Will
this new updated interchange attract more traffic through our area?
A - Traffic studies conducted during the preliminary
design phase predicted a small (1 percent) increase in the overall traffic
using the interchange as a result of the proposed improvements. It is expected
that this increase will mostly include interstate trucks taking advantage of
a better connection between New York and New England. Interstate-to-interstate
traffic on Route 300 will be reduced while the affect on local traffic using
Route 300 is estimated to be minor.
Q - Did
the improvements along Route 300 in 1998 help relieve traffic congestion? Was
Route 300 improvement work necessary?
A - The 1998 improvements to Route 300
were intended as an interim measure to improve operations along Route
300 until a comprehensive interchange improvement could be constructed.
Q - Will
the added traffic signals cause congestion on Route 300?
A - The additional traffic signals on Route
300 will subject traffic to a 37-second delay when compared to existing
conditions. The proposed conditions, although slower, will provide safer roadways.
Q - Will
the new access to the Thruway from Route 300 make it more difficult
for me to get to/from my business/ residence off of Stewart Avenue.
A - The new access to the Thruway will introduce
an additional phase at the traffic light to include left turn signals at the
Route 300/Stewart Avenue intersection. The revised signal operations will introduce
minor delays to the westbound Stewart Avenue approach to the intersection.
However, with the new signal arrangement, left turns from Stewart Avenue will
now be permitted. Southbound Route 300 traffic will experience minor delays
compared to its current unimpeded movement.
Q - The
new Tandem Trailer facility looks very large. Does this mean
a lot of trucks will use Route 300?
A - The new tandem trailer facility is sized
for 90 vehicles. By regulation, trucks using Route 300 will be restricted
to single semi-trailers. With the proposed improvements, the volume of trucks
using Route 300 will not exceed the current volume. Traffic analyses
indicate that eliminating the interstate traffic component will greatly improve
the safety of operations along the Route 300 corridor and reduce the volume
of large trucks by 30 percent.
Q - What
are the modern features that will be implemented at the Toll Plazas?
A - The new Toll Plaza will include a number
of features that will improve toll collection and safety, including higher
speed (20 mph) E-ZPass lanes, Dedicated Truck Lanes and an overhead walkway
that will eliminate the need for toll collectors to cross active lanes. New
style booths will also be installed to improve toll collector efficiency. Also,
an unmanned "E-ZPass Only" toll plaza will be constructed on the
Ramp to Route 17K for local access. Traffic using this lane will pass an E-ZPass
reader at ramp speed (30-35 mph).
Q - The
on-ramp from Route 17K to the Thruway is very convenient. Why
has it been eliminated?
A - The Route 17K off-ramp will be retained
for E-ZPass traffic only. With the proposed interchange, local traffic entering
the Thruway will be required to travel Route 300 to the vicinity of Stewart
Avenue, where it would enter the Thruway via a signalized intersection at Route
300.
Back
to top
|