Skip to main content
New York State Thruway Authority Home Click to return to NYS home page
New York State Thruway Authority

Highlights from the Design Report

The investigations identified the following transportation concerns.

  • Existing congestion and safety on Route 300 and at the Interchange 17 Toll Plaza will worsen to unacceptable levels under future traffic conditions. Operating deficiencies on the I-87 mainline, the I-87 ramps, and at the Route 300 ramp terminals will increase in severity.
  • The movement of people and goods in the area will continue to be negatively affected by the operational problems of the existing I-87/I-84 Interchange system.

Project Objectives

The primary objectives of the I-87/I-84 Interchange project are:

  • To provide a more efficient connection between I-87 and I-84 that provides acceptable levels of service through the year 2025 and maintains local access to and from the Interstate highways.
  • To provide interchange improvements that are cost effective and achievable with minimal impact to the community and the environment.

Alternatives

During the environmental review phase of this project, two alternatives were considered. They were:

No-Build Alternative

The No-Build Alternative provides for continued maintenance of the existing interchange roadways (I-84/Route 300/I-87), with no major improvements or repairs.

Build Alternative

The Build Alternative would reconstruct the Interchange to provide a more direct connection between I-84 and I-87. Local access from both Interstate highways would be provided through two new signalized intersections on Route 300.

The existing toll collection facility at Interchange 17 would be replaced by two modern toll plazas constructed within the Thruway Authority maintenance area. One plaza would serve traffic entering the Thruway (I-87) and the other plaza would serve traffic exiting the Thruway. An additional exit toll barrier would be provided to serve E-ZPass traffic from the northbound Thruway to Route 17K.

The Thruway Authority maintenance facilities and the State Police Headquarters would be replaced within the existing site. An improved tandem trailer facility would be constructed at Interchange 17 with better access to/from I-84 and I-87.

Under the Build Alternative the majority of construction would be completed within the boundaries of the Thruway Authority maintenance facility and the rights-of-way of I-87 and I-84. Minor strip takings are required from three undeveloped, commercially owned properties.

Summary of Design Investigations

Preliminary design investigations evaluated the transportation benefits and environmental impacts of the project alternatives. The results of the investigations are summarized below. Additional detail is provided in the Design Report.

  • Traffic and Safety

    Under the No-Build Alternative, the unsatisfactory traffic and safety conditions of the existing interchange would increase in severity as traffic volumes grow in the future.

    Under the Build Alternative, Interstate-to-Interstate traffic would no longer use Route 300 as the connection between I84 & I-87. The expanded and modernized toll barriers would increase capacity and reduce congestion and delays at the Newburgh Toll Area. The Build Alternative would also eliminate many of the existing conditions which contribute to the high rate of accidents within the vicinity of the interchange.
  • Air Quality

    Analyses of selected intersections were undertaken for the No-Build and Build Alternatives. The results indicate that no adverse air quality impacts are expected as a result of the project.
  • Noise

    Analyses of noise sensitive sites were performed for the No-Build and Build Alternatives. The results indicate that there will be no negative noise impacts at these sites, and the predicted noise levels of the Build Alternative would be lower than the No-Build Alternative.
  • Wetlands

    The Build Alternative would disturb approximately three acres of wetland areas under the jurisdiction of the U.S. Army Corps of Engineers. Replacement wetlands would be constructed as part of the project.
  • Water Resources

    Under the Build Alternative, there would be an increase in paved area, which would result in an increase in storm water runoff from the project area. To ensure that the increased runoff would not adversely affect the quality of nearby streams and lakes, retention basins would be constructed within the interchange.
  • Hazardous Wastes

    An Environmental Site Assessment revealed contaminants which exceed clean-up levels established by the New York State Department of Environmental Conservation (NYSDEC).  During construction, excavated materials will be tested and disposed of in accordance with NYSDEC requirements.
  •  Construction Impacts of the Build Alternative

    During construction there would be short-term impacts on the operations of Route 300, Route 17K and the interstate highways. The contract documents would include detailed maintenance and protection of traffic plans to minimize these impacts.

    Construction of the Build Alternative would also have short-term impacts on noise levels and air quality. Most of the construction activity would take place within the existing Thruway Authority maintenance site and existing highway right-of-way. Construction noise and air quality impacts on residential and commercial properties would be minimal. The construction specifications for the project would include requirements to further minimize construction nuisances such as construction dust and equipment noise