For The Week Starting Monday 06/30/2008
Syracuse Region

Mainline I-90
Between Exits Work Description Lane Closure Information Likely Impacts Comments
37 & 35  Bridge Work  West Left lane,
7pm to 6am Tuesday and Wednesday.

West Deceleration lane,
7pm to 6am Monday.

East Alternating right lane with the left lane,
7pm to 6am Monday.

East Left lane,
7pm to 6am Tuesday and Wednesday.

 
Moderate  None 

 
Impact Key
Impact Description
None None
Minimal Traffic moving at posted speed
Minor Traffic delayed up to 5 minutes more than normal time
Moderate Traffic delayed from 5 to 20 minutes more than normal time
Severe Traffic delayed 20 minutes or more over normal time


Scheduled Construction Lane Closures

For The Week Starting Monday 07/07/2008
Syracuse Region

Mainline I-90
Between Exits Work Description Lane Closure Information Likely Impacts Comments
33 & 34  Guide Rail Installation  West Right lane,
Wednesday 7:30 AM to 2:00 PM.

 
Minimal  None 
33 & 34A  Guide Rail Installation  West Left lane,
Wednesday 7:30 AM to 1:00 PM.

 
Minimal  None 
33 & 34  Bridge Work  West Alternating right lane with the left lane,
Monday 8:00 PM to Tuesday 6:00 AM. Tuesday 8:00 PM to Wednesday 6:00 AM. Wednesday 8:00 PM to Thursday 6:00 AM. Thursday 8:00 PM to Friday 6:00 AM. Friday 10:00 PM to Saturday 6:00 AM.

 
Minimal  None 
34A & 34  Shoulder Work  West Both lanes,
Wednesday, 7:00 PM to Thursday 7:00 AM. Thursday 7:00 PM to Friday 7:00 AM. Friday 7:00 PM to Saturday 7:00 AM. Moving closure Wednesday and Thursday.

West Both lanes,
Tuesday 8:00 PM to Wednesday 6:00 AM. Moving Closure

West Left lane,
Monday 8:00 PM to Tuesday 6:00 AM.

East Both lanes,
Wednesday, 7:00 PM to Thursday 7:00 AM. Thursday 7:00 PM to Friday 7:00 AM. Friday 7:00 PM to Saturday 7:00 AM. Moving closure Wednesday and Thursday.

East Left lane,
monday 7:00 PM to Tuesday 7:00 AM.

 
Minor  None 
37 & 35  Bridge Work  West Deceleration lane,
Tuesday 7:00 PM to Wednesday 6:00 AM.

West Left lane,
Monday 7:00 PM to Tuesday 6:00 AM.

East Left lane,
Monday 7:00 PM to Tuesday 6:00 AM.

East Deceleration lane,
Tuesday 7:00 PM to Wednesday 6:00 AM.

 
Moderate  None 
39 & 40  Paving  West Left lane,
Wednesday 7:30 AM to 2:00 PM.

West Left lane,
Thursday 7:30 AM to 2:00 PM.

 
Minor  None 
41 & 40  Bridge Painting  West Right lane,
Monday 7:30 AM to 2:00 PM.

West Left lane,
Tuesday 7:30 AM to 2:00 PM.

East Left lane,
Wednesday 7:30 AM to 2:00 PM.

 
Minor  None 
41 & 40  Paving  East Left lane,
Tuesday 7:30 AM to 2:00 PM.

 
Minor  None 

 
Impact Key
Impact Description
None None
Minimal Traffic moving at posted speed
Minor Traffic delayed up to 5 minutes more than normal time
Moderate Traffic delayed from 5 to 20 minutes more than normal time
Severe Traffic delayed 20 minutes or more over normal time